Providence Portland Medical Center Central Utility Plant

2006 Vista Awards Providence Portland Medical Center Central Utility Plant
Portland, OR

(Click on an image to see a larger copy)

Project size
Number of square feet: 43,000 square feet
Number of beds: N/A
Project Budget
Initial budget: $31 million
Actual budget: $31 million
Construction Schedule
Start date: August 2004
Finish date: October 2005

David Grigsby
Project Architect
Zimmer Gunsul Frasca Partnership
Portland, OR

Richard Gerber
Principal
CDi Engineers
2006 Vista Awards Lynnwood WA

Kimberly Krull
Principal
Sparling
Portland, OR

Greg Holloran
Project Superintendent
Turner Construction Company
2006 Vista Awards Portland, OR

Joe Webb
Construction Manager
Providence Health System
Portland, OR