2008 Vista Award Recipient
New Construction
Presented to an organization that has constructed a new facility essentially from the ground up. The new facility may be connected to an existing facility, but the building must have its own identity and be a new space.
Luther Midelfort Mayo Health Systems
Fairbanks, Alaska
Project Information
Number of square feet: 57,600
Number of beds: N/A
Project budget: $36 million
Actual cost: $32.6 million
Start date: May 23, 2004
Completion Date: May 31, 2005
| Team Members | |
| Bert Bell | President, GHEMM Co. Inc., Fairbanks, AK |
| Royal Bidwell | Project Coordinator, Greater Fairbanks Community Hospital Foundation, Fairbanks, AK |
| Robert Gould | Associate Administrator,
Chief Fiscal Officer and Operations,
Fairbanks Memorial Hospital, Banner Health, Fairbanks, AK |
| Martha L. Hanlon | AIA, Principal Architect, Martha Hanlon Architects Inc., Fairbanks, AK |
| Jon T. Lundquist | Associate Administrator, Plant Operations, Support and Facilities, Fairbanks Memorial Hospital, Banner Health, Fairbanks, AK |
| Gretchen O’Mahoney | Director, Radiology, Fairbanks Memorial Hospital, Banner Health, Fairbanks, AK |